Blair Hawkins' Work Journal
Fri 7-8-2016. Private Clinics 2570B and 2445. Replace more ceiling tiles in waiting room.
Global Health Corner Building basement. Remove mold/mildew soaked HVAC duct.
Thu 7-7-2016. Private Clinics 2570B and 2445. Replace ceiling tiles where spray-on asbestos is above drop ceiling.
Thornton A238. Create a plastic barrier for crew to install HVAC ducts.
Wed 7-6-2016. Kerchof steam tunnel. Bring to completion.
Global Health Corner Building basement. Remove mold/mildew soaked HVAC duct. To be scheduled.
Thornton A238. Create a plastic barrier for crew to install HVAC ducts.
Tue 7-5-2016. Kerchof steam tunnel. All but half dozen pipe sections are hauled to asbestos dumpster. Finish tomorrow and clean up with vacuum.
Mon 7-4-2016. Independence Day Holiday.
Payday 7-15.
1st Week Jun 27 || M 8 | T 8 | W 8 | Th 8 | F 8 || Sa | Su = 40 Hours.
2nd Week Jul 4 || M 8 | T 8 | W 8 | Th 8 | F 6 || Sa | Su = 2 UL.
Payday 7-1.
1st Week Jun 13 || M 8 | T 8 | W 8 | Th 8 | F 8 || Sa | Su = 40 Hours.
2nd Week Jun 20 || M 8 | T 8 | W 8 | Th 8 | F 8 || Sa | Su = 40 Hours.
Payday 6-17.
1st Week May 30 || M 8 | T 8 | W 0 | Th 8 | F 8 || Sa | Su = 8 UL.
2nd Week Jun 6 || M 8 | T 8 | W 8 | Th 8 | F 8 || Sa | Su = 40 Hours.
Payday 6-3.
1st Week May 16 || M 8 | T 9.5 | W 12 | Th 11 | F 11.5 || Sa 11 | Su 11 = 34 OT.
2nd Week May 23 || M 8 | T 8 | W 8 | Th 4 | F 0 || Sa 0 | Su 0 = 12 UL.
The correction occurs only when leave and overtime occur in the same week, not 2-week pay period. If it did, I would
opt for keeping the 12 hours UL and getting only 22 hours OT. Explanation Week 29.