Fr/Sa/Su 22/23/24 January Blizzard of 2016, aka Snowzilla and Winter Storm Jonas. Three 12-hour shifts of shoveling, snow-blowing, driving box truck. Red rings around legs from UVA-issued Redwing winter safety boots not made for walking.


Thu 1-21-2016. Thornton A008. Cut up and haul away the pile of wood.

Travel to Milton Airport to pick up rope stands with concrete base.

Prepare for predicted winter storm Jonas.


Wed 1-20-2016. Chemistry 237. Day 8. Take down plastic enclosure for plumbing repair above drop ceiling where spray-on asbestos is located. Neg Air #4 back in storage.

JAG School. Day 2.

Thornton A008.


Tue 1-19-2016. JAG School. Day 1. Remove 2 layers of vynil floor tile, the first layer asbestos tile. Remove floor mastic. Full containment with shower decon. Neg Air #2.

Chemistry 237. Vacuum plastic enclosure. Prepare to take down. Installed Wed 1-13-2016.


Mon 1-18-2016. Newcomb Hall 3rd floor entrance. Punch 3 exploratory holes in non-asbestos plaster ceiling.

2-hour study module for Sexual Harassment Title IX. Test score 90%.

Help Sign Shop assemble sign for Shelburne Hall.

Old Cage is now divided into temporary offices and shops. We're in the process of moving back to renovated shop.