Fri 5-27-2016. Day off.


Thu 5-26-2016. Pavilion 5 crawl space. Spread special plastic for later plumbing work.

Future job. Chemistry 166, 409, 410A, 410B. Carpet / asbestos tile / asbestos mastic.


Wed 5-25-2016. MSB 2614. Remove wet ceiling tile for leaking pipe, fiberglass insulation. The spray-on above the drop ceiling is asbestos.

Thornton A218. Remove small section of carpet / tile / mastic for drilling holes in floor. Create a hole in asbestos plaster ceiling above the drop ceiling.

Campbell Hall School of Architecture. 4thh floor under renovation. Remove asbestos counter top and sink with acoustic spray-on asbestos on under side to dampen the sound of a dripping faucet.

Pavilion 5 crawl space for Thursday. Spread special plastic for later plumbing work.

MR-4 Room 1035. Deliver 4 disposal bags, some plastic, 2 piece rolls of red tape. The lead panels in the wall are coupled with plywood and black mastic said to be negative for asbestos.


Tue 5-24-2016. MR-4 Room 1035. Remove lead panels glued to sheetrock panels above drop ceiling, where spray-on is cellulose, not asbestos. Next phase is to remove lead panels in the walls.


Mon 5-24-2016. Bonny Castle. Remove lead paint 3 plywood panels under kitchen awning. Create exploratory hole in asbestos plaster ceiling.


Payday 6-3.

1st Week May 16 || M 8 | T 9.5 | W 12 | Th 11 | F 11.5 || Sa 11 | Su 11 = 34 OT.

1st Week May 16 || M 8 | T 9.5 | W 12 | Th 11 | F 11.5 || Sa 11 | Su 11 = 34 OT.

2nd Week May 23 || M 8 | T 8 | W 8 | Th 4 | F 0 || Sa 0 | Su 0 = 12 UL.

2nd Week May 23 || M 8 | T 8 | W 8 | Th 4 | F 0 || Sa  | Su  = No correction.

The correction occurs only when leave and overtime occur in the same week, not 2-week pay period. If it did, I would opt for keeping the 12 hours UL and getting only 22 hours OT.


Payday 5-20.

1st Week May 2 || M 8 | T 8 | W 8 | Th 8 | F 8 || Sa  | Su  = 40 hour work week.

1st Week May 2 || M 8 | T 8 | W 8 | Th 8 | F 8 || Sa  | Su  = No correction.

2nd Week May 9 || M 8 | T 8 | W 8 | Th 0 | F 8 || Sa 8 | Su  = 8 UL | 8 OT.

2nd Week May 9 || M 8 | T 8 | W 8 | Th 8 | F 8 || Sa  | Su  = 40 hour work week.